What are the installation steps of aluminum alloy doors and windows?

[china aluminum industry network] many people in the home improvement, often more time and energy are placed on the selection of home, especially the purchase of aluminum alloy doors and windows, often ignore the aluminum alloy doors and windows installation, in fact, aluminum alloy The installation of doors and windows is also very important. There is a slight difference. In the future, various problems will arise. Therefore, it is necessary to understand the installation knowledge of aluminum alloy doors and windows. Today, Xiao Bian has organized aluminum alloy doors and windows for everyone. The installation steps, let's understand together!

铝合金门窗的安装步骤有哪些

1, marking positioning:

(1) According to the orientation, size and elevation of the doors and windows in the plan drawings, the edges of the doors and windows shall be measured on both sides of the centerline of the doors and windows. If it is a multi-storey or high-rise building, use the line of the top door or window as the standard, use the line sinker or theodolite to lower the edge of the door and window, and scribe the symbol at each level of the door window, and cut out the individual non-straight mouth.

(2) The horizontal orientation of doors and windows shall be measured upwards from the level of + 50cm above the floor and the height of the lower skin shall be measured upwards. It is necessary to adhere to the same height of the window skin at each floor.

2, aluminum alloy window water device:

According to the requirements of the construction drawings, the hanging water shall be fixed on the aluminum alloy window, and the orientation shall be ensured and the device shall be solid.

3, anti-corrosion treatment:

(1) If there is a requirement for the anticorrosion treatment plan outside the door/window frame, it shall be handled according to the planning requirements. If the plan does not require, it may be painted with anti-corrosion coating or posted with plastic film for maintenance to avoid direct contact of the cement mortar with the aluminum alloy doors and windows. , Electrochemical reaction occurred, corrosion of aluminum alloy doors and windows.

(2) When installing aluminum alloy doors and windows, if iron fittings are selected to be fixed, the metal parts used to join the iron pieces, fixing pieces, etc. must use stainless steel parts, otherwise it is necessary to carry out anti-corrosion treatment to avoid electrochemical reactions, corrosion of aluminum alloy Doors and windows.

4, aluminum alloy doors and windows in place:

According to the planned window and door positioning line, aluminum alloy door and window frames are installed, and the quality standards such as the horizontal, vertical and diagonal lengths of the door and window frames are timely adjusted, and then temporarily fixed with a wooden wedge.

5, aluminum alloy doors and windows fixed:

(1) When iron is embedded on the wall, the iron feet of the aluminum alloy doors and windows can be directly welded to the embedded iron on the wall directly, and the welding place needs to be treated with rust prevention.

(2) When there are no iron parts embedded in the wall, metal anchor bolts or plastic expansion bolts can be used to fix the iron feet of the aluminum alloy doors and windows to the wall.

(3) When there is no iron on the wall, drill holes with 80mm depth and 6mm diameter can be drilled on the wall. Use L-shaped 80mm×50mm 6rmn steel bars to stick 108 cement slurry on the long end. , and then into the hole, until the 108 cement slurry final coagulation, and then the aluminum alloy doors and windows of the iron foot and embedded 6mm steel welding.

6, the gap between the door and window frame and the wall between the treatment:

(1) After fixing the aluminum alloy door and window device, it is necessary to carry out the screening project inspection. After passing the inspection, the gap between the door and window frame and the wall body shall be treated according to the planning requirements.

(2) If the planning is not required, the elastic insulation material or glass wool felt strips can be used to layer and fill the gaps. External and external surfaces should be filled with 5-8mm deep slots to fill caulking ointment or sealant.

7, door and window fan and door window glass device:

(1) Door and window sashes and door and window sashes shall be installed after inspection of the exterior surface of the opening wall.

(2) After the sliding door and window are fixed on the door and window frame device, the window and door sash with a good glass door will be integrated into the chute inside the frame, and the gap with the fan can be adjusted.

(3) Swing the door and window with the frame and the fan frame to assemble the wall, and then fix the glass after the device is fixed, that is, adjust the gap between the frame and the fan first, then insert the glass into the fan and adjust the orientation, inlay the sealing strip and Sealant.

(4) The floor spring door shall be fixed after the door frame and the ground spring host grounding device are fixed. First insert the glass into the door frame and place it into the frame together. Adjust the gap of the frame fan and fill in the sealing strip and sealant of the door glass.